Soma® Safe Timeline to Success

Vivax Medical Corporation

Timeline for successful implementation 6-7 weeks 

Example Start Date: Monday October 1

Week

1-2

Demonstration
Week

3

Trial 3-5 days with 1-2 patients
Week

3-4

Feedback from trial, questions, and concerns addressed
 Week

4

Contract formalized and discussed
Week

4

Introduction to our operations personnel
Week

4

Schedule Nursing Grand Rounds and MD Grand
Week

4-5

Vivax Medical customizable policies, procedures examples provided, sent to management for changes, approval and finalized
Week

5-6

In-Service Schedule
Week

5-6

Quiz
Week

5-6

Evaluation of SSE Patient Care and Safety Program; grading and certificates sent out
Ongoing  Weekly equipment quality checks to ensure positive patient outcomes

Estimated Completion Date: Monday November 12

Estimated Savings as of December 31 – $27K per month